15-Minute UPS Backup for Laboratory Instruments in China
The Context & Challenge
The laboratory needed uninterrupted power for its instruments and equipment. The backup system had to work with the Delta UPS host and meet a 15-minute runtime requirement at a reported load current of 300 A.
LEOCH Solutions
LEOCH supplied eight PU512V100 lithium battery sets for the UPS installation, providing backup power for the laboratory instruments and equipment.
Key Results
The project summary reports that the system can support a 300 A load current for 15 minutes, meeting the stated backup time requirement.
-
Client Industry
Laboratory and testing
-
Location
China
-
Date of Deployment
August, 2024
-
Products Deployed
PU512V100
-
Total Scale
8 Sets